Hall Lane / County Road / Old Rough Lane Schedule



Diversion Plan

Phase

Outline Dates

Action

Why?

Impact

Phase 1

Start 22 Oct

- Dec

Close Old Rough Lane to vehicles between Old Rough Lane and Scoter Road

Reduce use of Invasive 4 Way Temporary Traffic Signals from 20 weeks to 8 weeks

No access through Old Rough Lane at Junction of County Road





Maximise and Optimise Safe Working Practices

Maintain access for pedestrians at all times through junction





All other vehicle movements unaffected

Phase 2

Start Dec

- New Year Period

None - All Traffic Management to be removed off site


Restore Junction for Xmas Period - Minimise Impact on ALL Users throughout Xmas Period

None - back to previous Traffic Signals layout

Phase 3

02 Jan 19

- early March 19

Introduce 4 Way Temporary Traffic Signals at County Road Junction for 8 Weeks

This is the only Safe way to remove old signals and introduce upgraded signals

Disruption to Vehicular Traffic due to use of temporary traffic signals at junction




Maximise and Optimise Safe Working Practices and maintain pedestrian access


Phase 4

One week following Phase 3

Resurfacing of whole junction

New Surfacing for Whole Junction

Disruption to Vehicular Traffic due to use of temporary traffic signals at junction




Configure New Traffic Signals and Safety Audit





Finish off project


Road Works